Many of you already know Casey, or know of him. He is a 30-year veteran of the component industry who lives in Indiana. I became acquainted with him listening to him speak on wall panel production at a BCMC Show. Later, while working for MiTek in St. Louis, I was able to visit him while he was Operations Manager for the Stock Building Supply plant in Franklin, IN. Casey is currently a consultant for RevisionLLC. I consider Casey to be one of the best critical thinkers in our industry. He graciously agreed to an interview for this newsletter. Here are some of the highlights of that interview.

 

Core Strategy for Production Management

 

GI: Is there a particular concept or strategy that you consider critical to effective production management?

 

CC: I think it is essential to have an accurate scheduling system with measurable benchmarking.

 

GI: There are a lot of different ways to do scheduling and benchmarking. How do you choose which one to use?

 

CC: Any method is acceptable, as long as you are constantly working to improve it. You want a create a system that is not going to cost you a lot of time and money to maintain and you need to integrate this system into your manufacturing process. You don’t want a system that is dependent on one person keeping a lot of records. In that type of system, if that person misses a day – nothing is recorded.

 

GI: Scheduling can be done with 3x5 cards on a board in the production office. Is this an acceptable scheduling system?

 

CC: Jobs have lots of different characteristics, and a name and a number doesn’t tell you much. If you take the “cards on the board” idea to the next step by making your floor truss jobs blue and your roof truss jobs yellow, well, that’s more at least a little more information. The more sophisticated you want to be, the more characteristics you will want to measure. I want to be able to use those characteristics to learn more about what we do well, and what we don’t do so well. I also like to look at the various stages a job goes through, and create benchmarks for each stage. When we do that, we have a better chance of discovering where our bottleneck is. It’s important when measuring that the reporting be accurate. Without it, you can’t tell if a variation in the data is ‘normal’ or a special case that merits investigation.

 

Truss production is picking, cutting, manufacturing and packaging. It took me a while to fully realize that when I had finished building the trusses, the product was not ready to ship. A number of steps, such as sheathing gables and getting the paperwork and the hangers together, are all part of the ‘packaging’ process. I also decided it was important to know, for each job, how long the trusses were sitting in my yard before they were shipped.

 

GI: How did you find that useful?

 

CC: It begins with the notion that you don’t want to build something and have it sit in the yard where you can’t get paid for it. In measuring “days sitting in the yard,” you may discover how accurate your customer’s scheduling system is. Sometimes it reveals the habits of the sales rep. Did he get it into production before it was needed just so he wouldn’t have to manage it anymore? When I was working with production builders, it was very helpful to have a complete report of what was sitting in the yard, and how long it had been sitting there. If he was hammering me with “When I am I going to get Lot 12?” I could respond with “Why don’t to also take Lot 14? You ordered that two weeks ago and it has been sitting in my yard for a week?!” Measurements like “days in yard” help you determine if you have a system problem or a people problem.

 

‘Just in Time’ Production

 

GI: Is a ‘just in time’ production process practical for truss production?

 

CC: Absolutely.

 

GI: What about the argument that you need to get a day or two ahead on the saw? In a JIT production system, if your saw goes down, aren’t you at risk of having to shut down altogether?

 

CC: A lot of people think production is a cutting issue. They give sawyers incentives and overtime that encourage them to get ahead, then the pieces sit in the yard for a day or two. I think you need to eliminate tying up capital like that. There’s also the hidden cost of the extra time the guy who stages material for the tables takes to find the needle in the haystack of cut pieces. The guy at the back end of the saw should know exactly where to take the pieces to, and the guy getting the pieces for the tables should know exactly where they are without hunting around.

 

Ideally, you have people cross trained so you can put more people where your current constraint is. And if you are measuring things and know your expectancies, you can foresee when you should only be operating one saw or when to move your sawyer to another task. Getting way ahead with the saws is an example of doing ‘a wrong thing right.’ On the other hand, implementing a lean manufacturing process and finding you are running short of pieces for the tables would, in turn, be an example of doing the right thing wrong. Having clarity about what the ‘right’ and ‘wrong’ things is tough, and an ongoing process.

 

To the point about managing “in case the saw goes down;” how often does that really happen? If it happens fairly often, is it a problem with the equipment or are you just not doing what you should be to maintain it? When I managed a plant, my rule was, “If I can’t get the part in three hours, I’ll buy an extra one and put it on the shelf.” I was confident the cost of those extra parts was cheap insurance compared to the cost of that piece of equipment being down for a day or more.

 

How much does it cost you when a piece of equipment goes down? What does equipment down time cost you annually? Grappling with these things isn’t easy. If it was, everyone would do it. On the other hand, sometimes people just need a little illumination about the right things to do - and it gets them headed in the right direction. Many times there is already someone in the plant who knows where an improvement could be made, but just doesn’t act on it; in some cases it’s because he is too invested in the current process.

 

One attitude that is so important within the organization is taking care of your internal customers. If you are the saw department, are you doing everything you can to make sure that your customer, the table guys, have everything they need? Do they know where to get work for the next job? Is it clearly marked? Do they know where it should go on the production line? Treating the next guy in the manufacturing process as your customer and constantly trying to improve the service you provide to him will make your overall process better and better over time.

 

Business Management

 

GI: Do you think there are any common misconceptions or blind spots in the industry right now?

 

CC: I think CM’s are blaming poor bottom lines on the competitiveness in the industry right now, rather than looking for opportunities to become the low cost provider. Think about:

 

· What was my estimate cost?

· What was my design cost?

· What was my build cost?

· Did I get the job to the site on time?

· What ‘value adds’ am I performing that I don’t have to be doing?

· What ‘value adds’ do I need to do that I’m not doing?

 

By looking at each of these carefully, we can all find areas where we can lower costs. Also, by really working on safety, it is possible to save thousands of dollars a year on workers comp claims. By making a study of ‘errors and omissions,’ you can eliminate many of them. It wasn’t until I looked hard at my errors, that I realized that most were coming from design. That let to steps to reduce the errors, and lower our costs.

 

GI: Any thoughts on the effective use of the software tools that are out there?

 

CC: Scheduling and inventory control software should be used to their fullest capacity.

 

GI: Why don’t you think people make better use of the software they have?

 

CC: Two reasons. First, they don’t know how to use them. Second, they are fearful that the software will tell the whole story and they will end up looking bad.

 

An example of the type of measurement that today’s software has the potential of providing: We figured out there was a fairly high degree of probability that certain plates sizes that were going to be used at a certain locations on our 110’ line, for example we used a lot of 5x5 plates at the peaks and many times the peaks fell in roughly the same place. We put a bunch of those plates in bins at those locations on the table, and then only picked the plates that were “special.” It saved a bunch of time on plate picking. We couldn’t have done that without the software’s help.

 

With inventory in particular, I’ve seen several things derail implementation. In some cases we just don’t want to do the work it takes to set it up and maintain it. In others, the purchasing people don’t really want to work that closely with manufacturing. I’ve even seen cases where it just comes down to not having everyone on board with the plan. Managing inventory is crucial, and the software can help a lot, but it has to be used in order to help.

 

 

Lineal Saws, Auto-jigging, ROI

 

GI: Lineal saws: are they the future, or simply a nice compliment to a component saw? What about auto-jigging?

 

CC: If you are talking about replacing a component saw with a lineal saw, be sure to consider the considerable changes that probably will need to be made to the layout of your facility. Lineal saws have several facets, making it hard to make a definitive statement about them. Let’s look at it this way, we want to make greater profits, right? Greater profits come through less inventory, less cost, and more throughput. Lineal saws can help in each of those areas but they need to be thoughtfully implemented with each of those factors in mind. The ROI on lineal saws and auto-jigging is highly dependent on the average quantity per setup your plant runs.

 

GI: How do you go about analyzing ROI?

 

CC: When looking at ROI, I like to boil it down to man hours saved vs. how much more (or less) work I am going to get out. I am also mindful of the ‘hidden savings’ that come into play when we can improve accuracy, quality, and safety. For example, if I cut more accurately I’ll probably be able to set up a little faster and produce a product that performs better in the field.

 

 

What’s Coming in the Future?

 

GI: What do you see coming in the future?

 

CC: I see one guy who does all the design work; trusses, panels, EWP, the whole thing.

 

GI: A lot of people say they don’t have enough time – we will always need more than one person working on a job to make the delivery on time.

 

CC: I think we are guilty of not giving our people time to learn new things. Look at BCMC – a lot of owners but very few designers.

 

GI: What else?

 

CC: I see CM’s providing more things for the customer, things like rake ladders and stud counts even when we don’t supply wall panels. And I think more plants will be doing wall panels. I also foresee software that ties together all my equipment in the plant with all my business processes.

 

 

You can contact Casey Carey at casey1212@att.net.